Report No.

337

Discipline/Origin

Drilling
No origin

Well

Shrek
6507/5-9 S, 6507/5-9 A

Date created

2019/10/21
2239 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Operational
Negative

Deepsea Nordkapp


What happened in Top hole:
When running conductor 0.5 m higher stick-up was observed.
Base plan was to hold the conductor irrespective.
Attempted to wash and work to bottom, no go.

What Was Planned

Space out to TD the well to place the conductor on bottom.

What Was Learned

Since it was always intended to hold the conductor whilst the cement set up, evaluate to plan for TD being conductor length plus 1 m rat hole. This would then reduce the risk of a high stick up.

What Actions Are Required

Add 1 m reter rat hole to top hole TD to have sufficient margin to correct stick-up if needed.